PSA spots irregularities during Martin Linge FSO audit
Tuesday, Aug 07, 2018
On 25 July 2018, Petroleum Safety Authority (PSA) carried out an audit of the follow-up of materials handling, cranes and lifting on Martin Linge B.

Objective

The audit formed part of our follow-up of the development project for the Martin Linge field. The objective of the audit was to assess whether the requirements for materials handling, cranes and lifting on Martin Linge B were being met during the conversion of and operational preparations for the facility.

Result

The audit detected non-conformities in the areas of procedures for cranes and lifting operations, completion of cranes and training.

Equinor has been given a deadline of 3 September 2018 to report on how the non-conformities will be addressed.

For more information, please visit: http://www.ptil.no